Crane beam approach slab Ch 1275, Hidd Port, 29Jan2008
البحرين
محافظة المحرق
Crane Beam Piling, A…
Crane Beam, 5thApr20…
Crane beam piling, 2…
Crane beam piling, 2…
Concreting piles to …
Reinforcing to Crane…
First concrete to cr…
Concreting of crane …
Piles to be cut off …
Crane beam Ch930. Hi…
Block paving under l…
Installation of cabl…
Service corridor - 1…
Ongoing crane beam w…
StormwaterS3 crossin…
Completed crane beam…
Sub station Ch1370 o…
Sub Stations SS14 an…
Sub Grade prep betwe…
Welding crane rail, …
Block paving to quay…
3 quay cranes and 6 …
3 quay cranes and 6 …
Asphalt to crane rai…
Stormwater excavatio…
Crane beam piling, 2…
End of sandstorm, cr…
First concrete to cr…
Ongoing reinforcing …
Lowering reinforceme…
Crane beam reinforci…
Crane beam Ch930. Hi…
Crane beam reinforci…
Crane beam piles rea…
Sub Grade Preparatio…
Crane rail works wit…
Block Paving from qu…
Block paving under l…
Shuttering for Storm…
Welded crane rail, C…
Sub Station SS14 SS1…
Crane rail works wit…
Block paving to cran…
Line marking to quay…
Sub Base preparation…
Reefer Gantry founda…
It rained!!! Crane R…
Shutters for Reefer …
First concrete to cr…
Impressum